A week from the inside: the day-by-day schedule

Week S37, which in the season plan was a single figure, becomes an executable schedule here: which line processes which fruit each day, to fill every sailing before its cut-off.

This is week S37's optimal plan: each line has its fruit and its sailing assigned before every cut-off.

Day × line schedule
Fruit of the day
Forecast
45
50
55
60
55
45
Actual
·
·
·
·
·
·
The actual fruit is what the plants process and what fills the sailings
North Plant · 34 t/day
Mon
Tue
Wed
Thu
cut-off R
Fri
cut-off F
Sat
cut-off S
use
Line A · 20 t/d
20R
20R
20R
18X
20F
20S
98%
Line B · 14 t/d
14R
14F
14F
14F
14F
14X
100%
People
41/42
41/42
41/42
39/42
41/42
41/42
South Plant · 30 t/day
Line A · 18 t/d
·
18R
18F
18F
18F
18X
83%
Line B · 12 t/d
12S
·
12S
12S
12S
12S
83%
People
15/34
22/34
36/34
36/34
36/34
36/34
Processed / capacity
46/6472%
52/6481%
64/64100%
62/6497%
64/64100%
64/64100%
Cold storage
·
·
·
·
·
·

Each cell: tonnes assigned to the line that day · the letter is the destination sailing · X = extra fruit · Cold storage = fruit arrived but not yet processed (projected for the days ahead)

Sailings of the week

Schedule on track: all three sailings are on time

Processed 0 of 310 t committed

This is the week's optimal plan. Start it to see, day by day, how reality tests it.

The week's plan

Start the week to follow the schedule day by day and see how it adjusts to the actual fruit.